Server maintenance: phase B
Scheduled Maintenance Report for ASPEX - Statuspage
Completed
We see a small amount of servers of phase A having some issue, since the day after the change. To ensure the stability of the environment, we have decided to postpone the maintenance. We will inform you when a new date is set.
Posted Mar 02, 2021 - 13:35 CET
Scheduled
During the change window of Thursday, March 4 maintenance work will be carried out on the servers on our own datacenter of phase B. During this process, the servers will be rebooted several times. Servers running on the Azure datacenters are not impacted.

This maintenance will be carried out on Thursday, January 7 in Acceptance and on Thursday, February 4 on the servers of phase A.

Several management agent will be upgraded. Please contact your technical contact for more information about this maintenance or its impact on your environment.
Posted Jan 05, 2021 - 12:44 CET
This scheduled maintenance affected: ASPEX Datacenter (Servers / Virtual Machines).